MSG Local Administered Project Exception Report  
  
Material Type GroupMaterial Type DescriptionLAP Exception
Aggregate Aggregate Base Course - E When placement is on Greenway or Multi-Use Path density requirement is 92% for Nuclear or Conventional method
Asphalt Asphalt Bases & Pavements - E Form 610-9 revised mix per QMS. When placement is on Greenway or Multi-Use Path compaction - 85% every 5,000 ft, minimum of one per project
Concrete Concrete, Class A - E Must use NCDOT approved mix. When used in lieu of Class-B application, testing frequency should be 1 per 100cy placed
Concrete Concrete, Class B - E When placement is on Greenway or Mult-Use Path must use NCDOT approved concrete mix. Minimum of one set of cylinders per project to test compressive strength
Fencing Materials Fence Post, Metal - B Type 6 certification and Buy America required. Ornamental fencing approved by Municipality. Split rail fencing may be purchased from local sources.
Fencing Materials Fencing Accessories - B Type 6 certification and Buy America required. Ornamental fencing approved by Municipality. Split rail fencing may be purchased from local sources.
Fencing Materials Fencing Fabric, Woven Wire - E Type 6 certification and Buy America required. Ornamental fencing approved by Municipality. Split rail fencing may be purchased from local sources.
Fencing Materials Fencing Fabric/Wire - E Type 6 certification and Buy America required. Ornamental fencing approved by Municipality. Split rail fencing may be purchased from local sources.
Fencing Materials Fencing Wire, Barbed - E Type 6 certification and Buy America required. Ornamental fencing approved by Municipality. Split rail fencing may be purchased from local sources.
Grading Borrow Material For Quality - E Sample required if Borrow is not from an approved source. Minimum of one embankment density and one subgrade density per project. Embankment should meet 90%, subgrade 92%.
Grading Earthwork Excavations - Borrow - E Sample required if Borrow is not from an approved source. Minimum of one embankment density and one subgrade density per project. Embankment should meet 90%, subgrade 92%.
Grading Embankment from Unclassified - E Sample required if Borrow is not from an approved source. Minimum of one embankment density and one subgrade density per project. Embankment should meet 90%, subgrade 92%.
Grading Rock Embankment (Cubic Yards) - E Sample required if Borrow is not from an approved source. Minimum of one embankment density and one subgrade density per project. Embankment should meet 90%, subgrade 92%.
Grading Rock Embankment (Tons) - E Sample required if Borrow is not from an approved source. Minimum of one embankment density and one subgrade density per project. Embankment should meet 90%, subgrade 92%.
Grading Subgrade - B Sample required if Borrow is not from an approved source. Minimum of one embankment density and one subgrade density per project. Embankment should meet 90%, subgrade 92%.
Grading Subgrade - E Sample required if Borrow is not from an approved source. Minimum of one embankment density and one subgrade density per project. Embankment should meet 90%, subgrade 92%.
Guardrail Guardrail Anchor Cable - B When placement is not adjacent to vehicle traffic, must come from approved producer, verify Heat numbers, no FIR required.
Guardrail Guardrail Anchor Unit - B When placement is not adjacent to vehicle traffic, must come from approved producer, verify Heat numbers, no FIR required.
Guardrail Guardrail Anchor Unit - Chemical Check - B When placement is not adjacent to vehicle traffic, must come from approved producer, verify Heat numbers, no FIR required.
Guardrail Guardrail Backup Plates - B When placement is not adjacent to vehicle traffic, must come from approved producer, verify Heat numbers, no FIR required.
Guardrail Guardrail, Aluminum Beam - E When placement is not adjacent to vehicle traffic, must come from approved producer, verify Heat numbers, no FIR required.
Guardrail Guardrail, Hardware - B When placement is not adjacent to vehicle traffic, must come from approved producer, verify Heat numbers, no FIR required.
Guardrail Guardrail, Plastic Block - B When placement is not adjacent to vehicle traffic, must come from approved producer, verify Heat numbers, no FIR required.
Guardrail Guardrail, Steel Beam - B When placement is not adjacent to vehicle traffic, must come from approved producer, verify Heat numbers, no FIR required.
Guardrail Guardrail, Steel Beam - E When placement is not adjacent to vehicle traffic, must come from approved producer, verify Heat numbers, no FIR required.
Guardrail Guardrail, Steel Post & Block - B When placement is not adjacent to vehicle traffic, must come from approved producer, verify Heat numbers, no FIR required.
Guardrail Guiderail, Cable - E When placement is not adjacent to vehicle traffic, must come from approved producer, verify Heat numbers, no FIR required.
Guardrail Guiderail, Cable, Hardware - B When placement is not adjacent to vehicle traffic, must come from approved producer, verify Heat numbers, no FIR required.
Guardrail Temporary Steel Beam Guardrail Terminal Sections - B When placement is not adjacent to vehicle traffic, must come from approved producer, verify Heat numbers, no FIR required.
LIghting and Elect. Light Standard, High Mount - B Submittals should be reviewed by NCDOT and/or Municipality for compatibility with existing infrastructure
LIghting and Elect. Lighting and Electrical Materials - B Submittals should be reviewed by NCDOT and/or Municipality for compatibility with existing infrastructure
LIghting and Elect. Lighting and Electrical Materials - E Submittals should be reviewed by NCDOT and/or Municipality for compatibility with existing infrastructure
Signal Traffic Signal Materials - B Submittals should be reviewed by NCDOT and/or Municipality for compatibility with existing infrastructure
Signal Traffic Signal Materials - E Submittals should be reviewed by NCDOT and/or Municipality for compatibility with existing infrastructure
Utilities Pipe, Utility, ABS - E Submittals should be reviewed by NCDOT and/or Municipality for compatibility with existing infrastructure
Utilities Pipe, Utility, ABS - M Submittals should be reviewed by NCDOT and/or Municipality for compatibility with existing infrastructure
Utilities Pipe, Utility, Accessories - B Submittals should be reviewed by NCDOT and/or Municipality for compatibility with existing infrastructure
Utilities Pipe, Utility, Accessories - E Submittals should be reviewed by NCDOT and/or Municipality for compatibility with existing infrastructure
Utilities Pipe, Utility, Accessories - M Submittals should be reviewed by NCDOT and/or Municipality for compatibility with existing infrastructure
Utilities Pipe, Utility, Ductile Iron - E Submittals should be reviewed by NCDOT and/or Municipality for compatibility with existing infrastructure
Utilities Pipe, Utility, Ductile Iron - M Submittals should be reviewed by NCDOT and/or Municipality for compatibility with existing infrastructure
Utilities Pipe, Utility, Ductile Iron, Fittings - E Submittals should be reviewed by NCDOT and/or Municipality for compatibility with existing infrastructure
Utilities Pipe, Utility, Ductile Iron, Fittings - M Submittals should be reviewed by NCDOT and/or Municipality for compatibility with existing infrastructure
Utilities Pipe, Utility, Polyethylene - E Submittals should be reviewed by NCDOT and/or Municipality for compatibility with existing infrastructure
Utilities Pipe, Utility, Polyethylene - M Submittals should be reviewed by NCDOT and/or Municipality for compatibility with existing infrastructure
Utilities Pipe, Utility, PVC - E Submittals should be reviewed by NCDOT and/or Municipality for compatibility with existing infrastructure
Utilities Pipe, Utility, PVC - M Submittals should be reviewed by NCDOT and/or Municipality for compatibility with existing infrastructure
Utilities Pipe, Utility, Steel - E Submittals should be reviewed by NCDOT and/or Municipality for compatibility with existing infrastructure
Utilities Pipe, Water, Copper - E Submittals should be reviewed by NCDOT and/or Municipality for compatibility with existing infrastructure
Utilities Pipe, Water, Copper - M Submittals should be reviewed by NCDOT and/or Municipality for compatibility with existing infrastructure
Utilities Pipe, Water, Polyethylene - E Submittals should be reviewed by NCDOT and/or Municipality for compatibility with existing infrastructure
Utilities Pipe, Water, Polyethylene - M Submittals should be reviewed by NCDOT and/or Municipality for compatibility with existing infrastructure
Number of Records: 52